Final piece of long delayed Navy Pier Flyover takes shape over Chicago River; on track for completion by year’s end

The project, the crown jewel of the revamped lakefront path, is in the home stretch of construction.

SHARE Final piece of long delayed Navy Pier Flyover takes shape over Chicago River; on track for completion by year’s end
merlin_92529930.jpg

Construction on the Navy Pier Flyover is seen Tuesday morning, Aug. 18, 2020. The flyover, an elevated walking and biking path near Navy Pier, is set to open by the end of 2020.

Pat Nabong/Sun-Times

The end is in sight (fingers crossed).

The final pieces of the Navy Pier Flyover are coming together, and the project, which has experienced repeated delays, is on track for completion by year’s end.

On Tuesday, the steel supports that will undergird a 20-foot wide path that’s being added to the east side of the Lake Shore Drive Bridge were being painted “Chicago Bordeaux” — a familiar color to anyone who’s ever crossed a bridge in Chicago.

The new pathway over the river will be raised and lowered along with the main bascule bridge that’s spanned the river since the 1930s to accommodate boat traffic.

Key components to complete the pathway over the river will be arriving in Chicago from Georgia in the next several weeks, according to Larry Mestan, the engineer who’s managing the project for the city.

Several of those components will be assembled into two smaller bascule bridges on either end of the new pathway to allow clearance for the large bascule bridge to go up and down without slamming into the bridge houses.

merlin_92529960.jpg

The Navy Pier Flyover, under construction Tuesday morning, Aug. 18, 2020, is an elevated walking and biking path near Navy Pier that is set to open by the end of 2020.

Pat Nabong/Sun-Times

For years, cyclists and pedestrians have crossed the river on a narrow stretch of sidewalk next to busy lanes of traffic on the lower deck of the two-tiered Lake Shore Drive Bridge.

As this work is being completed, pedestrians and cyclists will continue to use a lane of the Lower Lake Shore Drive Bridge that’s normally used by cars.

A completed portion of the flyover has for months provided a much improved experience by carrying users over Grand and Illinois streets, eliminating the street-level crossings.

Chicago Department of Transportation spokesman Mike Claffey said Tuesday that completion of the last phase of project construction on the project amounted to the “whipped cream or gravy on top.”

Construction on the Flyover Project began in 2014 and was originally slated for completion in 2018; then the middle of 2019; then the end of 2019; then the spring of 2020; now the end of 2020.

Repairs to the Depression-era bridge are taking place alongside work on the Flyover Project. Some of those fixes were unexpected and contributed to delays in the much-anticipated project.

“Anytime you’re dealing with a structure this old, you can’t find some stuff until you actually start taking it apart,” said Mestan.

The $64 million project has drawn repeated criticism for taking longer to build than the Golden Gate Bridge (four years).

The Latest
The teenager was shot in the 8700 block of South Burley Avenue and was in critical condition, police said.
White & Co. finished fifth in the league in defensive efficiency last season. They entered Saturday’s game against New Orleans sitting at 21st. If the Bulls are going to start getting this season back on track, the guard knows where it needs to start.
Alabama is again the top dog in the SEC — and perhaps headed to the College Football Playoff — after ending Georgia’s 29-game winning streak with a 27-24 victory for the conference title.
Beauvillier, making his Hawks debut after a trade from the Canucks, played well on the top line Saturday. But Bedard’s tally went down as the Hawks’ only goal in a 3-1 loss.
Davis, who finished with 17 points and nine assists, has immediately made the Blue Devils a much stronger team than anticipated.