Company that got $295M in Chicago city business lied to get deals, City Hall says

The city wants to ban Joel Kennedy Constructing Corp. from city contracts, saying it falsely claimed that more than half of its work was done by city residents and that it’s based in Chicago.

SHARE Company that got $295M in Chicago city business lied to get deals, City Hall says
City Hall Inspector General Joseph Ferguson found that Joel Kennedy Constructing Corp. engaged in a “fraudulent scheme” involving four city contracts — including ordering some employees to lie that they live in Chicago so they could help meet a city residency requirement.

City Hall Inspector General Joseph Ferguson found that Joel Kennedy Constructing Corp. engaged in a “fraudulent scheme” involving four city contracts — including ordering some employees to lie that they live in Chicago so they could help meet a city residency requirement.

Max Herman / Sun-Times file

Over the past three decades, a family-owned construction company got 32 contracts from the city of Chicago to repair sewers and install water mains — work that cost taxpayers more than $295 million.

Now, in a federal lawsuit against the company that was initiated by a whistleblower, City Hall accuses Joel Kennedy Constructing Corp. of lying and cheating to get six contracts since 2013, including falsely claiming to be a Chicago company when it’s actually headquartered in Waukegan.

According to the lawsuit, the company also submitted phony paperwork showing 50% of the work was done by Chicago residents, as required by a city ordinance.

But an investigation by City Hall’s inspector general’s office found that Kennedy’s company submitted its weekly payroll records only after first deleting the names of its suburban employees, making it wrongly appear Chicago residents had done more than half of the work.

The inspector general’s office also found that the company gave city officials phonied-up records showing employees were city residents who actually lived outside Chicago, providing bogus addresses for workers.

“The contractor’s fraudulent scheme misrepresented over 70,000 labor hours across four contracts,” according to a report from Inspector General Joseph Ferguson. “The contractor encouraged and, in some cases, mandated that employees who lived outside of Chicago nonetheless acquire government documents with Chicago addresses so that they could count toward compliance. In other cases, workers were unknowingly assigned Chicago addresses, including the address of the company’s general counsel, on certified payroll submitted to the city.”

Ferguson recommended that City Hall bar Kennedy and his company from getting any future city work, a process the Lightfoot administration is pursuing.

Shannon Andrews (above), Mayor Lori Lightfoot’s chief procurement officer, is moving to ban Joel Kennedy Constructing Corp. from getting any city contracts, saying it “engaged in multiple fraudulent schemes to evade the city’s [Chicago residency ordinance] requirement.”

Shannon Andrews (above), Mayor Lori Lightfoot’s chief procurement officer, is moving to ban Joel Kennedy Constructing Corp. from getting any city contracts, saying it “engaged in multiple fraudulent schemes to evade the city’s [Chicago residency ordinance] requirement.”

Provided

Kennedy’s company “engaged in multiple fraudulent schemes to evade the city’s [Chicago residency ordinance] requirement and to avoid the assessment of damages for failure to comply with the CRO requirements,” according to a letter that Shannon Andrews, Mayor Lori Lightfoot’s chief procurement officer, sent Kennedy on Feb. 10.

Kennedy and his lawyers didn’t respond to messages seeking comment.

They have asked a federal judge to toss out City Hall’s lawsuit, arguing that the residency ordinance — which dates to Mayor Harold Washington’s administration — is unconstitutional.

Angelo Milazzo — a Park Ridge resident who, records show, owned 10% of Kennedy’s company while a project manager there between 1987 and 2015 — blew the whistle on Kennedy by filing the lawsuit four years ago.

Milazzo stands to share in any financial damages the city might be awarded from Kennedy.

His lawyers won’t comment on the suit or about why Milazzo left the company.

Lightfoot’s law department joined Milazzo’s lawsuit in June 2019.

That came three days after City Hall had given Kennedy another contract, this one for $4.7 million for sewer work at Division Street and Lawndale Avenue in Austin.

City officials won’t discuss the suit.

Megan Vidis, a spokeswoman for the city’s water management department, says City Hall never gave Kennedy the go-ahead to start work on the Austin contract, “and no work was performed on that project.”

The city’s lawsuit says Kennedy “evaded city requirements that ensured that city residents would be hired to perform a certain percentage of the hours of work generated pursuant to these contracts.”

The suit also says Kennedy’s “principal place of business” is in Waukegan and not, as it told city officials, at 5901 N. Lincoln Ave. The lawsuit says claiming a Chicago address as its headquarters improperly allowed Kennedy to get a Chicago “business preference” over other companies that had sought the city contracts.

“Had the city known that these claims were false, the city would never have entered into the . . . contracts with [Kennedy] and/or would have terminated the . . . contracts with [Kennedy] and/or would have refused to pay [Kennedy’s] false and fraudulent invoices,” the lawsuit says.

In moving to keep Kennedy from getting future city work, City Hall cites four contracts it says his company cheated to obtain:

  • $79.5 million for water-main construction between Addison Street and North Avenue, a deal awarded in January 2013.
  • $76.9 million for water-main construction north of Addison, a job awarded in January 2013.
  • $4 million for sewer improvements at Damen and Albion avenues in West Ridge, a contract awarded in July 2013.
  • $1.9 million for sewer improvements along Augusta Boulevard in Humboldt Park, a deal the city gave him in October 2016.

The city’s lawsuit cites those deals and also two more projects:

  • $26.4 million for water main projects north of Madison Street, a contract awarded in May 2012.
  • $8 million for the private drain program for homeowners north of Madison, a job awarded in March 2009.

City Hall Feb. 10, 2021, letter to Joel Kennedy

The Latest
The crowd waited several minutes before the result was reviewed by the stewards and declared official.
In the eighth, Michael Busch tripled, and Patrick Wisdom, who had homered earlier, singled him home for the run that proved to be the difference in the Cubs’ 6-5 win.
Ball exercised the $21.4 million player option for next season. The hope is that he can overcome three left knee surgeries since 2022 and be available by fall camp.
Manager Craig Counsell said Suzuki likely will have a rehab assignment but Bellinger might not. Both could be activated from the injured list this week.
Tommy Pham gave the Sox the lead with an RBI single. After a three-hour delay, Tanner Banks needed 39 seconds to strike out pinch hitter Ivan Herrera looking to end the game.